A 1940s house reworked around a growing family

1940s house renovation in Otara (Ashton Ave/Street) – cover photo

Suburb

Otara

Services

Home RenovationsKitchen & Bathroom Renovations

Duration

Four months on site

What the owners wanted

A young family had outgrown the layout. The kitchen was a closed room at the back, the only bathroom was failing, and the rear of the house had a lean-to addition that had never been done properly. They wanted more usable living space without losing the character of the front of the villa, and they could not move out.

What made it specific

Villas of this age rarely give up their surprises at the site visit. Here the rear addition turned out to be sitting on inadequate foundations, and the original wall linings hid a mix of old wiring and previous alterations. Because the family were staying, the programme had to keep a kitchen and a bathroom available at all times, and dust had to be kept out of the two bedrooms at the front.

What we did

{"type"=>"root", "children"=>[{"type"=>"paragraph", "children"=>[{"type"=>"text", "value"=>"Rear reconfiguration: removed the lean-to, re-piled and re-levelled the rear of the house, and rebuilt it as a single kitchen and living space."}]}, {"type"=>"paragraph", "children"=>[{"type"=>"text", "value"=>"New kitchen: relocated plumbing and power, coordinated the cabinetmaker and benchtop, and rebuilt the ceiling line across the new space."}]}, {"type"=>"paragraph", "children"=>[{"type"=>"text", "value"=>"Bathroom rebuild: full strip-out, framing repairs where the old shower had leaked, re-waterproofed and re-tiled."}]}, {"type"=>"paragraph", "children"=>[{"type"=>"text", "value"=>"Services: rewired the affected areas, upgraded the board and replaced original plumbing runs that were reachable."}]}, {"type"=>"paragraph", "children"=>[{"type"=>"text", "value"=>"Character retained: front rooms left intact, with new skirtings, architraves and floor junctions matched to the originals."}]}, {"type"=>"paragraph", "children"=>[{"type"=>"text", "value"=>"Staging: a temporary kitchen in the dining room for three weeks, and the bathroom done before the kitchen so the family never lost both."}]}]}

Key decisions

{"type"=>"root", "children"=>[{"type"=>"paragraph", "children"=>[{"type"=>"text", "value"=>"Sequencing was the main decision on this job: the bathroom was rebuilt before the kitchen so the family never lost both rooms at once, and a temporary kitchen ran in the dining room for three weeks."}]}, {"type"=>"paragraph", "children"=>[{"type"=>"text", "value"=>"When the rear addition's foundations proved inadequate and old wiring was found behind the linings, both were priced as variations and agreed before work proceeded, rather than absorbed quietly."}]}]}

The outcome

The rear of the house now works as one space, with the kitchen where the family spends most of its time. The bathroom is sound and the wiring is safe. The front of the villa looks the way it always did. Two variations came up during the job: the foundation work under the old addition, and additional rewiring once the linings came off. Both were priced and agreed before they proceeded.

“They found rot under the bathroom floor in the first week. We got a photo, a price and an explanation the same day, and it never became an argument.”